Tuesday, 25 June 2013

Site Visit 24.06.13

 All existing ironmongery reviewed on site- revised schedule to be issued. Digilocks in general to be disabled where key operated lock also present- to make compliant with Part B/ Fire strategy.

 Carpet to NW0.06 discussed. Currently down to be retained but now room has been cleared it has revealed lots of staining. Request for pricing to replace to be raised

 Panel damaged to NW0.06. Request for pricing to replace to be raised

 Client sanitary supplies have been removed for decorating. CVA to liaise with client regarding reinstatement/ replacement

 Door ID.15 damage to both faces. Request for pricing to replace to be raised- otherwise filled prior to decoration.

 Existing slab to entry area bowed. BRAC to install water bar/ position door set to align with external cladding
 CVA/ BRAC detail to entry discussed. Instruction still to be raised for modifed ramp with improved drainage and handrail now omitted.

 Softwood bead to panels rotten- CVA to liaise with client regarding replacement

 Fascia decoration underway/ window installation and priming underway

 Underside of water tank to Gents WC exposed- timber to be replaced? CVA to discuss with client

 Cistern replacement? CVA to discuss with client

 Urinal to be cleaned- Action BRAC

Existing high level bracket not removed by client- to be retained to NW0.05