Fascia decorations to be completed
White paint around ramp to be completed
Redundant light fittings to be removed- areas made good
Ramp/ slabs complete
Redundant light fittings on fascia- ditto
Fire door keep shut signs required to all doors off of protected route only- to be applied to both leaves (where relevant) and both sides. Confirmed with AIS
Existing blind to be refitted- slightly undersized due to previous joinery- but should eliminate glare
Electrical works to be completed
Minor touching in of decorations- ceilings various locations as noted on site
Touch in decs over new door classroom 1
Rooflights- some eased- some broken and not repaired. BRAC to review if further repairs can be carried out
Ramp timber complete- awaiting strips to top surface
Decoration required around existing fan- Male WC