Snagging: Visit 1. 11.07.13

 If alarm is redundant to be removed and fascia made good

 Cill to have additional coat of paint

 Low level fascia board to have additional layer of paint
 
  High level fascia board to have additional layer of paint

 Redo filler to patch repair and recoat with masonry paint
 
Block downpipe/cap

Handrails to be continuous- complete with mired radius

 Ditto

 Fix felt high level to flat roof

 Complete solar film to EW.24 & EW.23

 Complete fire rated glass installation EW.23

 Denso tape/ low level repair to RWP

 Remove nails to external cladding

 Fix downpipe back to cladding

 Secure board/ back mastic seal

 Infill missing bead to window

 Touch in decorations

Infill piece/cover panel to step

 Touch in decorations

 Stray cable to EW.05

 Post to be removed by others after handover

Window bead missing to EW.04

 Replace split batten

 Replace cupped batten

 Fill holes/remove brackets

  Replace split batten

 If bulkhead light is not operational to be removed

 Softwood trim to be replaced as AI issued.

  Softwood trim to be replaced as AI issued.
 
 Ironmongery to be fitted to doors

 Obscured film to be removed from window

 Security alarm to be removed if redundant

 Oil filled radiators to be fitted to classrooms NW.015 and NW.016

 Dado trunking requires cover pieces to horizontal junctions

 Skirting to be filled - CVA to issue instruction
 
 Radiators to be cleaned

 Doors to be repaired where veneer broken. Doors to be varnished

 High level windows to NW0.14 to have solar film. CVA to instruct

 Fire alarm to ED.07 cannot be relocated as containment has been constructed above. AIS to inspect.

 Soffit to be redecorated

 High level hole to light fitting to be filled

 High level hole to light fitting to be filled

Cleaner's cupboard to be cleared and redecorated.